Skanska Secures $275 Million Data Center Project in Georgia, USA
Skanska has secured an additional contract worth USD 275 million (approximately SEK 2.8 billion) to build a new data center in Georgia, USA. The award comes from an existing client. Furthermore, it will be included in the company’s US order bookings for the fourth quarter of 2026.
The Skanska Georgia data center project involves constructing a new 48MW facility. The building will cover approximately 244,730 square feet (22,700 square meters). In addition, the project includes several important infrastructure components.
Project Scope and Infrastructure
The construction work includes the main building shell and interior fit-out. These spaces will accommodate technical operations, support facilities, and office functions.
Additionally, the project includes an ancillary water treatment building. This structure will cover approximately 860 square feet (80 square meters). It will support the facility’s operational requirements.
Construction Timeline
Construction began in November 2026. Meanwhile, the project is scheduled for completion in October 2028.
The additional USD 275 million award highlights Skanska’s continued collaboration with its existing client. Moreover, it strengthens the company’s position in the growing US data center construction market.
Growing Data Center Infrastructure Demand
Demand for data center infrastructure continues to increase across the United States. As digital services and computing requirements expand, large-scale facilities are becoming increasingly important.
Consequently, projects such as this 48MW development will contribute to expanding the country’s digital infrastructure. Furthermore, the contract represents another significant data center construction award for Skanska.
Project Highlights
- Company: Skanska
- Project Location: Georgia, USA
- Contract Value: USD 275 million (approximately SEK 2.8 billion)
- Data Center Capacity: 48MW
- Main Building Area: 244,730 sq. ft. (22,700 sq. m.)
- Water Treatment Building: 860 sq. ft. (80 sq. m.)
- Construction Start: November 2026
- Expected Completion: October 2028
- Order Booking: Q4 2026