San Diego Airport Central Utilities Plant Upgrade Success

San Diego Airport Central Utilities Plant Upgrade Success

Turner and FlatironDragados deliver critical infrastructure overhaul amid active airport expansion

April 2026 — Turner Construction Company and FlatironDragados have successfully modernized the Central Utilities Plant (CUP) at San Diego International Airport, while keeping the airport fully operational.

The upgrade forms a key part of the airport’s Terminal 1 replacement program, one of the largest ongoing airport construction projects in the United States.


Challenge: Upgrading critical infrastructure without shutdowns

The Central Utilities Plant, originally built in 1995, required a major upgrade.

The expansion created new demand, including:

  • 5,000 tons of additional cooling
  • 26 MMBH of heating capacity

However, the existing system lacked the capacity and efficiency to support this growth.

At the same time, the plant had to remain operational throughout construction.

In addition, tight site conditions near active airport facilities increased complexity.


Solution: Modernization over replacement

Instead of building a second plant, the team chose to upgrade the existing facility.

This decision reduced costs and simplified long-term operations.

Key upgrades included:

  • Replacing old chillers with higher-capacity units
  • Adding a heat recovery chiller and buffer tanks
  • Expanding cooling towers
  • Installing high-efficiency boilers
  • Upgrading pumps and control systems

Moreover, seven variable frequency drives improved energy efficiency and system control.


Minimizing disruption through smart execution

The project team used phased construction to maintain operations.

For example:

  • Only two chillers were taken offline at a time
  • Shutdowns were limited to short overnight windows

In addition, ACCO Mechanical prefabricated piping offsite to speed up installation.

Crews also installed a half-mile hydronic system connecting the plant to the new terminal.

They completed deep underground work, including road crossings, without interrupting traffic.


Results: Early delivery and uninterrupted service

The upgraded plant was completed four months ahead of schedule.

As a result, teams had extra time for testing and commissioning.

Importantly, airport operations continued without major disruptions.

Passengers experienced no service interruptions during construction.


Enhanced capacity and long-term efficiency

The modernized plant now delivers:

  • 5,000 tons of cooling
  • 26 MMBH of heating

It also features improved efficiency, redundancy, and advanced controls.

Therefore, the airport is better equipped to handle future growth.


Part of a larger airport transformation

The CUP upgrade supports the broader Terminal 1 redevelopment project.

Phase 1A is complete and includes 19 new gates.

Phase 1B is now underway and will replace the old terminal.

Once finished, Terminals 1 and 2 will connect post-security, improving passenger flow.

The full project is expected to be completed in 2027.


Outlook

This project highlights how complex infrastructure upgrades can proceed without disrupting operations.

It also demonstrates the value of phased construction and prefabrication in large-scale projects.

Latest from Blog

Jacobs Orange County Highway Improvements Unveiled

Jacobs Orange County Highway Improvements Unveiled

Jacobs has secured two major construction management contracts from the Orange County Transportation Authority (OCTA) to oversee highway modernization projects that aim to reduce congestion, improve safety, and enhance travel reliability across
Rock Island Bridge Entertainment District Unveiled

Rock Island Bridge Entertainment District Unveiled

How Multistudio Transformed Kansas City’s Historic Rock Island Bridge into a Vibrant Entertainment District A historic piece of American infrastructure has officially found a second life. Multistudio has successfully transformed Kansas City’s
Highmark Stadium Completion Celebrated by Officials

Highmark Stadium Completion Celebrated by Officials

Gilbane-Turner Completes New $2.1B Highmark Stadium for Buffalo Bills The Buffalo Bills have officially secured their long-term future in Western New York. Joint-venture construction partners Gilbane-Turner, alongside team and government officials, have
Bouygues Montenegro University Hospital Overview

Bouygues Montenegro University Hospital Overview

Bouygues Bâtiment International to Build New University Hospital in Montenegro In a major move to modernize healthcare infrastructure in the Balkans, Bouygues Bâtiment International—a subsidiary of Bouygues Construction—has secured a landmark design-and-build
Komatsu Global AI Framework: Enhancing Efficiency

Komatsu Global AI Framework: Enhancing Efficiency

Komatsu Ltd. has strengthened its global AI deployment framework to accelerate artificial intelligence adoption across its worldwide operations. The company plans to expand AI throughout its entire value chain. This includes product
Falcon 10X First Flight: A New Era Begins

Falcon 10X First Flight: A New Era Begins

Dassault Aviation’s Falcon 10X has successfully completed its first flight, marking the official start of the aircraft’s flight test program. The ultra-long-range business jet took off on June 19, 2026, from Bordeaux-Mérignac