Spectacular Bridge Swap Completed with Two Liebherr LR 11000 Cranes on Germany’s A42

Spectacular Bridge Swap Completed with Two Liebherr LR 11000 Cranes on Germany’s A42

Bottrop/Essen, Germany – In a remarkable display of engineering precision and heavy-lift capability, WASEL GmbH successfully completed a major infrastructure project involving the replacement of an aging concrete pipe bridge with a new steel construction. The operation, which took place on the A42 highway between Bottrop and Essen, was powered by two Liebherr LR 11000 crawler cranes, each with a 1,000-tonne lifting capacity.

Mission Highlights:

  • Two 220-tonne steel bridge sections lifted in tandem
  • Old concrete pipe bridge dismantled safely
  • Motorway closure shortened by two days
  • Seven Liebherr cranes involved in total

The bridge plays a crucial role in the region’s logistics network, connecting refineries to the Bottrop tank farm by crossing both the A42 highway and the River Emscher. The project was divided into two precise and time-sensitive phases.


Precision Tandem Lifts Offloaded from Ship

The new bridge segments — each 71 meters long, 7 meters wide, and 6 meters high — were manufactured by Schone & Bruns GmbH & Co. KG and shipped via the Rhine-Herne Canal. In a meticulously coordinated tandem lift, two Liebherr LR 11000 cranes, configured in SL11DBV setup with boom lengths of 96m and 84m, unloaded the 220-tonne segments from the vessel and placed them with centimeter accuracy in a designated pre-assembly area.

“Unloading from the ship with such a wide working radius was the biggest challenge,” said crane operator Florian Lauschke. “The cranes worked brilliantly — exactly what we expect from Liebherr.”


Bridge Replacement Completed Ahead of Schedule

In the second phase, one LR 11000 crane was dismantled, transported 1,000 meters via the A42, and reassembled at the installation site with a 72-meter boom. Simultaneously, the old concrete pipe bridge — composed of four segments — was safely dismantled using steel corsets to avoid structural damage during lifting.

The newly assembled steel bridge segments were transported using SPMTs (Self-Propelled Modular Transporters) to the site and lifted directly into position. Remarkably, the entire operation was completed two days ahead of schedule, thanks to the agility and lifting capacity of the Liebherr machines.

“The cranes impressed not only with their capacity but also with how quickly we could relocate and reassemble them,” said Viktor Hein, Project Manager at WASEL GmbH. “We achieved loads of up to 240 tonnes safely and precisely — even without using a ballast pallet.”


Collaborative Planning Key to Success

The entire project involved seven Liebherr cranes, including:

  • 2 × LR 11000 crawler cranes
  • LTR 1220
  • LTM 1230-5.1
  • LTM 1250-5.1
  • A 100-tonne mobile crane
  • A 450-tonne auxiliary crane

Günther Lohaus, Project Manager at Schone & Bruns, emphasized the value of detailed planning: “The goal was to minimize the motorway closure time. With strong coordination, a smart logistics concept, and highly reliable Liebherr cranes, we managed to complete the job ahead of schedule.”


About the Equipment

  • Crane Model: Liebherr LR 11000
  • Configuration: SL11DBV
  • Ballast: 130t central, 250t turntable, up to 450t derrick
  • Lifting Capacity: Up to 240t per crane
  • Working Radius: Wide span lifts with millimeter precision

A Model for Infrastructure Modernization

This successful bridge replacement sets a new benchmark for infrastructure projects involving large-scale lifting. The collaboration between WASEL GmbH, Schone & Bruns, and Liebherr highlights how strategic planning, engineering excellence, and the right equipment can drastically reduce project timelines and boost public infrastructure efficiency.

Latest from Blog

Asset Intelligence for Building Operations Explained

Asset Intelligence for Building Operations Explained

Glider and Virtual Helpdesk Partner to Bring Asset Intelligence to Building Operations Glider Technology Limited (Glider) and Virtual Helpdesk Limited (VHD) have announced a strategic partnership to help asset owners maintain accurate,
ACCIONA Sanitation Contract in Brazil Overview

ACCIONA Sanitation Contract in Brazil Overview

ACCIONA has signed a public-private partnership (PPP) contract with the Paraíba Water and Sewerage Company (Cagepa) to provide sanitary sewerage services across 85 municipalities in Paraíba, Brazil. The 25-year project will expand
Liebherr MK 88-4.1 Mobile Construction Crane Features

Liebherr MK 88-4.1 Mobile Construction Crane Features

Liebherr MK 88-4.1 Crane Supports Art Restoration on Paris’ Pont-Neuf A Liebherr MK 88-4.1 mobile construction crane from the Ponticelli group supported repairs to JR’s monumental art installation, ‘La Caverne du Pont-Neuf,’
I-285 Corridor Transportation Improvements Explained

I-285 Corridor Transportation Improvements Explained

Jacobs to Support Transportation Improvements Along Atlanta’s I-285 Corridor Jacobs will provide construction engineering and inspection services for transportation improvements along Atlanta’s I-285 corridor. The work will support roadway, bridge and safety
Freshwater-Free Concrete Initiative and Its Impact

Freshwater-Free Concrete Initiative and Its Impact

Fortune Recognizes Cemex for Freshwater-Free Concrete Initiative in Mexico Cemex has been included in Fortune’s 2026 Change the World list for its freshwater-free concrete initiative in Mexico. The program replaces freshwater used
Oak Hill Parkway Project Enhances Austin Mobility

Oak Hill Parkway Project Enhances Austin Mobility

Fluor Joint Venture Celebrates Opening of Oak Hill Parkway in Austin, Texas The $677 million project improves mobility, safety and connectivity along a major transportation corridor in southwest Austin. Fluor Corporation and